St. Therese

St. Therese   Concept Site Plan

St. Therese

On November 22, 2021, the City Council approved Saint Therese Communities request for approval of a Site Plan, Conditional Use Permit, and Preliminary Plat for a senior living community with 206 units and accessory complimentary uses, some of which will be open to the public. The proposed campus would be located on a newly created 12.88-acre parcel immediately south of City Hall. The City is the owner of the existing 78.88-acre parcel, and the requests includes a Preliminary Plat to create Lot 1, Block 1 that St. Therese will be acquiring as outlined in the purchase agreement.  
(City File No. 21-042) (PID 24-119-23-23-0001)

St. Therese Landscape Variance

On February 24th, City Council approved Saint Therese Communities' request of a landscape variance to allow fewer trees on the site for the senior living community project. The applicant proposes 181 trees including 159 overstory and 66 understory trees.
(City File No. 21-061) 

St. Therese Final Plat

Final plat and development contract for St. Therese was approved by City Council on April 28th. 
(City File No. 22-023)

Previous Meeting Dates

February 3, 2022: Planning Commission
February 24, 2022: City Council